Honkisaarenneva

Project details
Location
Kuortane, Finland
Capacity
34 MWp
Panels
65 000
Investment
~25.5 M€
Land area
50 ha
Phase
Construction
Project description
Solarigo is currently constructing an industrial-scale solar park on the former Honkisaarenneva peat production area in Kuortane, following the end of peat extraction. The project area covers approximately 50 hectares, and the park’s estimated annual electricity production is up to 31 GWh. This corresponds to the annual consumption of more than 1,500 electrically heated detached houses.
The solar park will be connected to the grid through a 31.5 MVA substation. Construction began in November 2024, with commissioning scheduled no later than February 2026.
The project has received support from the European Union and is part of the RENEWFM program. The views and writings expressed on this page represent only the views of Solarigo Systems Oy and do not necessarily reflect those of the European Union or CINEA (European Climate, Infrastructure and Environment Executive Agency), which provided the support. The aforementioned parties cannot be held responsible for the content of this site.
Project progress
Q2/2023
Development
The project started in cooperation with the landowners of Honkisaarenneva.
Following Solarigo Systems Oy’s initial examination, the project was deemed to have potential. Investment support for large demonstration projects of New Energy Technology was applied through the EU by the Ministry of Economic Affairs and Employment.
Q1/2024
Construction permit
Kuortane Honkisaarenneva Solar Park received a construction permit in March 2023.
Q2/2024
The EU supports the project
The European Union supports the project through the EU’s RENEWFM mechanism with € 4,131,273.
Q4/2024
Construction begins
Solarigo Systems Oy will begin the construction of the Honkisaarenneva solar park in November 2024. The initial work on site will include tree removal, foundation piling, and earthworks.
Q1/2025
Installations begin
The installation of mounting systems and solar panels at the Honkisaarenneva Solar Park began in February 2025. Tree removal and water protection structures were completed during the winter. Earthwork continues simultaneously with the installations.
Q2/2025
Foundation work nearing completion
The site’s piling is nearing completion, and construction of service roads is underway. Approximately 40% of the mounting systems and panel installations have been completed, and the project is halfway completed on schedule.
Q4/2025
Mechanical installations completed
All 55,536 panels have now been successfully installed. The substation has also been connected and commissioned to Fingrid’s 110 kV line. The project is progressing on schedule.
Got questions about the project?
Contact us – we’ll be happy to help.
Timo Tolonen
Project Manager