SOLJUVA
SOLAR PARK
PROJECT DESCRIPTION
Along Kuljuntie in Juva, there is a solar power plant with an area of about seven hectares. The construction of the solar park started in June 2023 and was completed in December 2023. The park produces approximately 4,500 MWh of solar electricity annually, which corresponds to the electricity consumption of Juva municipality. The municipality of Juva buys guarantees of origin from the park in an amount corresponding to its own electricity consumption, which means that the municipality's electricity needs are practically covered by solar electricity from Juva.
PANELS
9200
INVESTMENT M€
~ 3.5
STEP
PRODUCTION
LOCATION
JUVA
CAPACITY MWP
5
Add a Title
Lorem ipsum
Add a Title
Lorem ipsum
Development
The municipality of Juva entered into a land lease agreement for 25 years with Solarigo, with which the solar park project developed by Solarigo took first concrete step towards realization.
Around the same time, the municipality of Juva decided to buy guarantees of origin for solar electricity equal to its own consumption. Solarigo's sister company Lumme Energia is responsible for the brokerage of guarantees of origin.
12 / 2022
12 / 2022
PROGRESS OF THE PROJECT
Design
Solarigo made an investment decision on the solar park project at the beginning of 2023. Soil studies were carried out for the park, a deviation permit was applied for from Juva's building control administrative and the land was prepared for the installation of solar panels.
01 / 2023
01 / 2023
Construction
The first test piles were mounted in the soil of the Juva municipality solar park in May 2023. The actual construction began in June 2023.
06 / 2023
06 / 2023
Opening event
The municipality of Juva organized a naming contest for its solar park, as a result of which the park was named "Soljuva". The new solar park was celebrated by eating soup and drinking coffee, and getting to know the solar park among the municipality residents and the park's constructors.
05 / 2024
5 / 2024
Production
Juva municipality's solar park was connected to the grid in wintery landscapes in December 2023, ready to produce solar electricity in Juva municipality for the next 25 to 40 years.
12 / 2023
06 / 2023