SOLJUVA
SOLAR PARK

PROJECT DESCRIPTION

Along Kuljuntie in Juva, there is a solar power plant with an area of about seven hectares. The construction of the solar park started in June 2023 and was completed in December 2023. The park produces approximately 4,500 MWh of solar electricity annually, which corresponds to the electricity consumption of Juva municipality. The municipality of Juva buys guarantees of origin from the park in an amount corresponding to its own electricity consumption, which means that the municipality's electricity needs are practically covered by solar electricity from Juva.

PANELS

9200

INVESTMENT M€

~ 3.5

STEP

PRODUCTION

LOCATION

JUVA

CAPACITY MWP

5

Add a Title

Lorem ipsum

Add a Title

Lorem ipsum

Development

The municipality of Juva entered into a land lease agreement for 25 years with Solarigo, with which the solar park project developed by Solarigo took first concrete step towards realization.

Around the same time, the municipality of Juva decided to buy guarantees of origin for solar electricity equal to its own consumption. Solarigo's sister company Lumme Energia is responsible for the brokerage of guarantees of origin.

12 / 2022

12 / 2022

PROGRESS OF THE PROJECT

Design

Solarigo made an investment decision on the solar park project at the beginning of 2023. Soil studies were carried out for the park, a deviation permit was applied for from Juva's building control administrative and the land was prepared for the installation of solar panels.

01 / 2023

01 / 2023

Construction

The first test piles were mounted in the soil of the Juva municipality solar park in May 2023. The actual construction began in June 2023.

06 / 2023

06 / 2023

Opening event

The municipality of Juva organized a naming contest for its solar park, as a result of which the park was named "Soljuva". The new solar park was celebrated by eating soup and drinking coffee, and getting to know the solar park among the municipality residents and the park's constructors.

05 / 2024

5 / 2024

Production

Juva municipality's solar park was connected to the grid in wintery landscapes in December 2023, ready to produce solar electricity in Juva municipality for the next 25 to 40 years.

12 / 2023

06 / 2023

MORE INFORMATION

MIKKO
TUOMINEN

Senior Project Manager