top of page

PÄLKÄNE 
SKARTA

PROJECT DESCRIPTION

Finnish renewable energy developer Skarta Energy Oy is building a 5 MWp solar park in Pälkäne. Solarigo Systems Oy is responsible for the design, implementation and initial stage maintenance of the solar park. The solar park will consist of approximately 8,800 double-sided solar panels. The goal of the park is to be completed at the end of 2024.

PANELS

31,000

STEP

CONSTRUCTION

CONSTRUCTION

PÄLKÄNE

CAPACITY

5

Add a Title

Lorem ipsum

Add a Title

Lorem ipsum

Skarta teams up with Solarigo

Solarigo makes a site visit. Skarta chooses Solarigo as the designer, constructor and initial stage operator of the solar park.

09 / 2023

09 / 2023

PROJECT PROGRESS

Design

Solarigo begins the more detailed technical planning of the solar park and the implementation planning of the project. Solarigo makes a site visit.

10 / 2023

10 / 2023

DJI_0488.jpg

Landscaping

Solarigo begins landscaping works. The area is flattened and dried with drainage.

02 / 2024

06 / 2017

Panel installation

Solarigo begins the solar panel installations.

04 / 2024

04 / 2024

Rack installation

Solarigo begins installing solar panel racks.

03 / 2024

03 / 2024

MORE INFORMATION

JUHO
LASONEN

Senior Project Manager

bottom of page