KANNUS
SOLAR PARK, 
PUHURI

PROJECT DESCRIPTION

Kannuksen Hietakangas Oy, a subsidiary of wind power comapny Puhuri, is constructing the group's first solar power park in Kannus, Hietakangas. Solarigo Systems Oy is responsible for the overall EPC delivery of the solar park. After completion, the solar power park to be built in Hietakangas will consist of 8,784 double-sided solar panels. The solar park will be built on a decommissioned airport. Electricity transmission is carried out via two 33 kV substations with underground cables to the substation of the Kaukanen wind park owned by Puhuri's subsidiary. The designed service life of the park is 30 years. The park's construction permit is legally binding and it will be built on land owned by Kannus Hietakangas Oy.

PANELS

8800

STEP

PRODUCTION

LOCATION

KANNUS

CAPACITY MWP

5

Add a Title

Lorem ipsum

Add a Title

Lorem ipsum

Choosing a partner

Puhuri was looking for a partner for the implementation of its Kannus solar power plant project. Solarigo pays a visit to the project site in Kannus. Solarigo was selected a EPC constructor for the solar park in August 2023.

2023

2023

PROGRESS OF THE PROJECT

Land transfers

Solarigo started the preparatory work and land transfers in the area. The solar park was built on top of an airport, which was built on top of an old lake bed. It was necessary to build drainage in the area.

08 / 2023

08 / 2023

Mounting system installation

Piling and installation of the solar panel mounting system was completed in November 2023.

11 / 2023

11 / 2023

Transformers

The transformers were electrified in March 2023.

03 / 2024

03 / 2024

Panel installation

The installations of the solar panels and the DC side of Kannus solar park were completed in February 2024.

02 / 2024

02/ 2024

Introduction

Kannus Hietakangas solar power plant received a commissioning permit in June 2024 and the solar power plant project was completed on schedule.

06 / 2024

2019

DJI_0708.jpg

Production

Kannus Hietakangas solar power plant received a commissioning permit in June 2024 and the solar power plant project was completed on schedule. Solarigo acted as an EPC solution provider and the PV plant was handed over to Puhuri's Kannuksen Hietakangas Oy. 

03 / 2024

06 / 2024

MORE INFORMATION

JUHO
LASONEN

Senior Project Manager